Maple Avenue project update: Aug. 14, 2015
By Tom Turchi
Marshfield City Engineer
Phase 1: Maple Avenue from Veterans Parkway to Fourth Street and Third Street from Maple Avenue to Central Avenue
MARSHFIELD — Phase 1 is complete and has been reopened to traffic. On Friday, July 31, a groundbreaking was held for the Everett Roehl Marshfield Public Library project. Work on this project will be underway shortly.
Phase 2: Fourth Street from Central Avenue to Maple Avenue
The underground work on this phase is well underway. Earth Inc. had formed and then poured the concrete stormsewer structures yesterday. Work is underway for placement of select crushed material and open graded base course. Trimming of the open graded base materials is scheduled to begin on Wednesday, Aug. 19, and paving of half of Fourth Street is scheduled for Thursday, Aug. 20. Following this Earth Inc. will trim the other half of Fourth Street on Friday, Aug. 21, and pave on Monday, Aug. 24.
Curb and gutter, sidewalks, and colored crosswalks will be poured over the next two weeks following the mainline paving operations.
Phase 3: Maple Avenue from Sixth Street to Fourth Street and Fifth Street from Central Avenue to Maple Avenue
This portion of the project will begin as soon as East Fourth Street is reopened to traffic.
2016 construction of Second Street from Maple Avenue to Chestnut Avenue
The Marshfield Common Council has approved the concepts for the Second Street Corridor. Design work will begin soon based upon the conceptual designs linked here.