MARSHFIELD — Marshfield Utilities will begin a water main rehabilitation project beginning on April 24 on McMillan Street between Fig Avenue and Central Avenue. This water main project will require closing the north side of McMillan through the work zone. This project is expected to last until mid-July.
A detour will be signed for this work for eastbound traffic. Eastbound traffic will use Oak Avenue to Upham Street to Central Avenue. Westbound traffic will continue to use the south lanes of McMillan Street.
If there are questions concerning this project, call Marshfield Utilities at 715-387-1195.
Further road closure information can be found on the city’s website, ci.marshfield.wi.us.